The IEA's 2026 report, "Key Questions on Energy and AI," predicted global data center electricity consumption to rise from 485 TWh in 2025 to 950 TWh in 2030. It will account for approximately 3% of global electricity consumption in 2030. It also points out that power transmission and distribution grid and equipment supply constraints will affect the timing of facility operations.

In Japan, the OCCTO has separately recorded a peak power demand of 4.2 million kW and electricity demand of 30.8 billion kWh in FY2030 for new expansions of data centers and semiconductor factories. Of this, data centers account for 3.28 million kW and 24.3 billion kWh. This is an assumption based on application status, etc., and it is not confirmed that all facilities will operate.

The numbers seen by facilities and equipment manufacturers are different.

What to seeNumber to checkWhat you can learn from it
data centerGrid connection progress, operation start date, contract powerDid the plan approach the actual equipment demand?
data centerPUE, actual power usageFacility energy efficiency and operating status
equipment manufacturerTrends in orders/sales, order backlog and sales for data centersHas demand led to your own deliveries?
equipment manufacturerBusiness division profit margin, operating/investment cash flowWill increased production and delivery be profitable?

PUE is an indicator of the power efficiency of the entire facility, not the profit margin of the cooling equipment manufacturer. The Agency for Natural Resources and Energy has set a benchmark for specific operators in the data center industry to aim for a PUE of 1.4 or less by FY2030. Improvements in the efficiency of facilities and improvements in the profitability of supplier companies need to be confirmed separately.

Fuji Electric (6504) | Discloses sales growth for data centers

Fuji Electric supplies UPS systems and power receiving and transformation equipment. According to business strategy materials from May 2026, FY2025 data-center sales were 5.2 times the FY2020 level. However, the amount of profit for data centers is not indicated.

The company has increased its domestic UPS production capacity and has also started producing power distribution boards for data centers in Malaysia. Expanding supply capacity will help maintain sales, but it will also increase production costs and materials costs. The 5.2-fold sales figure does not disclose the contribution to profit.

Hitachi (6501) | Overall power network business numbers and HMAX

Hitachi Energy, a subsidiary of Hitachi, handles power grid equipment such as transformers. During the Q&A session regarding the fiscal year 2025 financial results, it was explained that the order backlog for Hitachi Energy as a whole increased by 33% year on year on a dollar basis, and sales increased by 26% year on year. These numbers do not represent orders or profits only for data centers.

On September 3, the company announced "HMAX Data Center," which integrates and monitors and operates data center power, IT, and cooling equipment, and began providing the first service to customers in North America. Prices are based on individual estimates, and the amount contributed to sales has not been disclosed.

The workload migration technology announced separately shows demonstration results at three facilities and future plans for deployment.